Is there a way for supplier to ask for a new delivery date in Ariba platform (for ecat / erfq / ertp) ?
For ERFQ, the supplier indicates the possible delivery lead time in his quote. For ECAT the lead time comes from the catalogs. In case the delivery date can not be respected the supplier need to send a message to the buyer. It is not feasible for the supplier to change the delivery date in Ariba platform in ST architecture.
Related Articles
Is it possible to issue a po with delivery in the past ?
is it possible to issue a po with delivery in the past ? For example at PR release the delivery date is in the future, but wasting time for approavl, the delivery date become in the past . Is the po relase in any case with delivery in the past ? If ...
Delivery need
In all the catalogue in MDM we have an item to show the Delivery need ( Express , rush.......) If I need to order a Board with ’express’ delivery, the below one should be a possible scenario Item Description Commodity Buyer code 1 Board FESP_BRD ...
Why in the approval flow for Catania we have another step after Philippe Chomienne ?
I’m testing the ERTP flow in Agrate PR11443: ERTP Agrate GP2 Why in the authorization loop for Catania we have another step after Philippe Chomienne Answer: By design for eRTP process, LEFC will always in the loop that's why we have NG Ph-Michael.
Which item should I select to create my e-rtp?
I was trying ERTP from AMK side. I have created two ERTP both needs Tan Yung Kong to approve as buyer, but inside KeePass, I do not have his login, can you help to add in? for me to complete the full process Answer : check your PR " AMK - ERTP ...
E-RFQ : in the live platform how end users can search their request ?
Thanks to find below some questions related to E-RFQ process : For test environment you have created some test lab to exercise them in the platform (data check file) , but in the live platform how end users can search their request ? they we will ...